Construction Updates, Routes VT-100 and VT-100A

The Vermont Agency of Transportation (AOT) is using accelerated construction to improve VT-100 in Plymouth and VT-100A, which spans Plymouth and Bridgewater.

DATE: November 5, 2021

VT-100 TRAFFIC IMPACT: The closure of VT-100 between Route 4 and VT-100A is anticipated to continue until the last week in November due to construction delays. Detour signs and message boards are in place to direct traffic. Please travel with caution. 

CONSTRUCTION ACTIVITIES: At bridge 114, L&D Safety Markings Corp., completed line striping on November 3rd, completing the Culvert 114 Project. At bridge 115, the contractor plans to pour two abutment footings today. Next week, construction of the headwalls and backfilling abutment footings will begin. 

LOCATION: VT-100 in Plymouth between VT-100A and Route 4.

PROJECTED COMPLETION: late November 2021



REMINDER: AOT has coordinated with the Department of Parks, Forests, and Recreation regarding the upcoming winter closure of Shrewsbury Road/ Old CCC Road. In light of the ongoing VT-100 closure, this year the road will remain open so long as weather permits, or until VT-100 is reopened. Stay tuned for an update when we anticipate the weather-driven closure.


At Culvert 115, abutment installation continued this week.

The VT-100A paving project has completed.

Contact Information.
Hannah Brockhaus
Public Information Consultant
802-673-1264 | hbrockhaus@fhistudio.com
This entry was posted in Community News. Bookmark the permalink.

Leave a comment